Cost plus contract
Contents |
[edit] What are cost plus contracts
Cost plus contracts are a form of contract whereby the contractor's costs are reimbursed along with a further payment, the nature of which depends on the form taken. As such these types of contract fall under the general category of cost reimbursable contracts, which might be considered higher risk from the client side because the final cost might not be specifically known or defined, although opinions differ on this point. The use of a guaranteed maximum price (GMP) along side cost plus has been one solution to this.
[edit] Cost plus, cost reimbursable and prime cost contracts
JCT has suggested that cost plus contracts, cost reimbursable contracts and prime cost contracts, are in fact the same, whilst others consider they differ as cost of work packages (the prime cost) are reimbursed, but the main contractor takes on risks of staffing, overhead costs and profit.
[edit] Prices and provisional sums
The disagreement or confusion may lay in the differences between the terminologies of fixed price, firm price, lump sum, stipulated sum, prime cost, guaranteed maximum price (GMP) and so on. The differences essentially being in the considered accuracy of the said amount, and which aspects are covered. For example the inclusion of defined provisional sums, undefined provisional sums, contingencies or allowances within the total might be for items of work that cannot be specifically priced by the contractor and as such may detract from accuracy leading to the use of GMP.
[edit] Types and terms describing cost plus contracts
There are a number of variations, as well as terms, that describe cost plus contracts, which also vary depending on the country of their use, some examples of these are described below.
[edit] Cost plus (Cost +) fixed percentage contract
Cost + Fixed Percentage Contract – Contractor will be entitled to Cost and profit percentage as agreed before.
[edit] Cost plus (Cost +) fixed fee contract
Cost + Fixed Fee Contract – Contractor will be entitled to Cost and Fixed fee as a profit
[edit] Cost plus (Cost +) fixed fee with Guaranteed Maximum Price Contract
Cost + Fixed Fee with Guaranteed Maximum Price Contract – Contractor will be entitled to Cost and Fixed fee as a profit, But the cost of the project should not exceed the agreed amount
[edit] Cost plus (Cost +) award fee contract
Cost + Award Fee contract is essentially the same as Cost + Fixed Fee Contract, allow the contractor to be awarded a fee usually for good performance.
[edit] Cost plus (Cost +) incentive fee contract
Cost + incentive fee contract is essentially a different description of the same as above, it may describe when the contractor is given a fee if their performance meets or exceeds expectations.
[edit] Multiple Incentive Contracts
Multiple Incentive Contracts are another term for incentive contracts that relate normally to the standard three areas of cost, quality and time, but could be expanded or defined in more detail.
[edit] Related articles on Designing Buildings
- Benchmarking.
- Building performance.
- Business plan.
- Contracts for Difference.
- Contingent liabilities.
- Cost plan.
- Cash flow.
- Cost reimbursable contract.
- Contingencies in construction.
- Contingency plan.
- Defined provisional sum.
- Energy performance contracts.
- Estimate.
- Fixed price construction contract.
- Guaranteed maximum price for construction contracts.
- Low Carbon Contracts Company.
- Lump sum contract.
- Milestones.
- Performance.
- Performance contracting.
- Performance incentives in contracts.
- Performance requirements.
- Preliminaries in construction.
- Prime cost contract.
- Project risk.
- Provisional sum.
- Retention.
- Undefined provisional sum.
- Value management.
- Whole life costs.
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.